Lessons for beginners

Learn to draw up a single-line diagram

The first time you see a single-line diagram, it looks like a tangle of lines, letters and numbers. Yet it follows a fixed logic: from the meter to the distribution board, and from there circuit by circuit to every light point and every socket. In ten short lessons you learn to draw up a single-line diagram yourself using that logic. No prior knowledge is needed. Together we draw one house in 1wire, from the first circuit to the plan for the inspection.

Two plans, one installation

After this lesson you know which two plans you draw up, what goes on them and how a diagram is built.

In Belgium, an electrical installation is described by two drawings that belong together. Together they form the plan that the inspector lays next to the installation during the inspection, and that then stays in the electrical file of the house. The plan must show the installation as it was actually built.

  • The single-line diagram shows how everything is connected: which protective device feeds which circuit, which cable runs there and which switches, lamps and sockets are on it. It says nothing about the location in the house.
  • The floor plan (situatieplan) shows where everything is: a plan of each floor with the same symbols on it.

The name “single-line” comes from the most important convention: one line represents the whole cable, even though in reality three, four or five conductors run side by side. How many there are and how thick they are is written in a code next to the line.

How a diagram is built

You draw the diagram from the supply to the loads. The supply comes in at the bottom: the grid operator's connection with the electricity meter. Next comes the distribution board, a long horizontal line. From that line the circuits run upwards, each with its own capital letter. You build each circuit from the bottom up: first the protective device, then the cable, then the switches and loads.

Below is what we are working towards: the complete diagram of the example house, a house with a ground floor and a first floor. In the next lessons you draw it yourself, piece by piece.

The finished single-line diagram of the example house in 1wire: at the bottom the meter, the 300 mA main switch and the earthing; on the board the hob A and the oven B, the 30 mA RCD C with the lighting D and E and the sockets F, and the 30 mA RCD G with circuits H to K.
The end result of this series of lessons, drawn in 1wire. Click to enlarge.
kWh

The supply: meter, 300 mA main switch and earthing. You draw it in lesson 3.

A–B

Two circuits directly on the board: the hob and the oven. That is lesson 4.

C

A 30 mA RCD with its own rail: the lighting (D, E) and the sockets (F). That is lesson 5.

G

A second 30 mA RCD: washing machine, dryer, dishwasher and bathroom (H to K).

Drawing an existing house? The example house follows the rules for a new installation, as they have been in the AREI since 1 June 2023. Your installation may look different, especially if it is older. That is not a problem: you always draw what is actually there. Lesson 5 shows what an older installation often looks like.

open your drawing sheet

  1. Open a new drawing sheet. 1wire opens on the Single-line diagram tab.
  2. On the left is the symbol library, Add components, grouped by type. On the right is the drawing sheet.
  3. The floor plan has its own tab, Floor plan. You will get there in lesson 9.

If you work without an account, 1wire keeps your drawing temporarily in your browser. With a free account, everything is saved online automatically.

Manual: a tour of 1wire → See an example diagram first →

Planning or tracing circuits

After this lesson you know which circuits you draw: for a new house you divide it into circuits, for an existing house you trace the circuits. That is the work that comes before drawing.

A circuit is everything behind one circuit breaker (often simply called a “fuse”): the cable, the switches, the lamps and the sockets. If you start drawing straight away, you often have to rearrange things afterwards. So first find out which circuits there are. How you do that depends on the house.

Dividing a new house into circuits

Go through the house room by room and list what will be there: light points with their switches, sockets and fixed appliances. Then divide them into circuits according to these rules:

  • Sockets: at most eight sockets per circuit. A double or triple socket counts as one.
  • Lighting: in a home with more than two rooms, compulsorily spread over at least two circuits, so the whole house doesn't go dark when one breaker trips. A split per floor is simple and clear.
  • Heavy fixed appliances: the hob, the oven, the washing machine, the dryer and the dishwasher each get their own circuit, as does any other fixed appliance of 2600 W or more.
  • Behind 30 mA: the bathroom, the washing machine, the dryer and the dishwasher, and since 1 June 2023 also the lighting and ordinary sockets. At most eight circuits per 30 mA RCD. Fixed appliances such as the hob and the oven may go directly behind the 300 mA (lesson 5).

An existing house: tracing the circuits

In an existing house, the division is already fixed. You trace it, starting from the distribution board:

  1. Record the board. Write down every RCD and every circuit breaker (or fuse) in the order they sit in the board, with what is printed on them. Lessons 4 and 5 explain where to find that. An existing label next to the breakers is a useful start, but check it.
  2. Switch off one breaker and walk through the house: which lamps no longer work, which sockets have no power? A small lamp or a socket tester makes this quick. Note everything per room.
  3. Switch it back on and repeat for the next breaker. That way each breaker gets its list of points: that is one circuit.
  4. Do the same with each RCD, to see which breakers sit behind it.

Only operate the switches in the board; don't open the board, any box or any socket. What you cannot see, such as the cross-section of a cable buried in the wall, ask an electrician.

How the example house is divided

This is how our example house, a new installation, is divided. 1wire assigns the letters A to K itself, according to the position of each circuit on the board. and are the two 30 mA RCDs: they get a letter too.

Circuit Purpose What is on it Behind
Hob the hob in the kitchen 300 mA
Oven the oven in the kitchen 300 mA
Lighting ground floor living room (2 lamps, 1 switch), stair light (switch at the bottom and the top) 30 mA (C)
Lighting first floor bedroom (3 switching points), landing 30 mA (C)
Sockets 5 socket groups in the living room, 2 of them double 30 mA (C)
– Washing machine, dryer, dishwasher each appliance its own circuit 30 mA (G)
Bathroom lamp with waterproof switch, socket 30 mA (G)
Tip: a real house usually has more socket circuits, for example for the kitchen and the bedrooms. We keep the example house deliberately small, so that each element appears only once.

the circuits and their names

In 1wire your division shows up in the Circuits tab: a list of all circuits with their letter, their number of points and their name. You fill in the names as you draw (lesson 6), and can look them up there at any time.

The Circuits tab with circuits A to K, their number of sub-circuits and their names, such as Hob, Lighting ground floor and Sockets. C and G, the RCDs, have no name.
The circuits of the example house, as they will appear in the Circuits tab.
Manual: the Circuits tab →

Drawing the supply

After this lesson the start of every diagram is on your drawing sheet: meter, main switch, distribution board and earthing.

The supply sits at the bottom of every diagram. It consists of four parts:

  • The electricity meter, a small rectangle with “kWh”. It measures how much energy the house uses and belongs to the grid operator.
  • The main switch, in a home usually a 300 mA RCD (differential switch). It switches off the whole installation in one go. On the device itself this value is often given in amperes: IΔn 0.3 A is the same as 300 mA.
  • The distribution board: the horizontal line from which all circuits will start.
  • The earthing, bottom left under the board. The two small cross strokes are the earth disconnect link, which lets the inspector disconnect the earth to measure it. The three ever shorter lines are the earth electrode in the ground.
The supply on the diagram: the earthing with earth disconnect link, the meter and the main switch labelled Type A, 300 mA, 3000, 2P - 40A.
The supply of the example house.
A two-pole RCD. Circled: the marking 40 A / IΔn 0,3 A, the blue test button T and the symbol for type A.
This is what a 300 mA main switch looks like: “40 A / IΔn 0,3 A”.

Which supply do you draw?

The type of connection determines how many conductors come in, and so usually also how many poles the main switch has. You write that on the diagram as 2P, 3P or 4P. The table gives the usual cases. When you draw an existing installation, copy what is on the main switch itself: sometimes, for example, there is a four-pole device on a three-phase supply without neutral, connected according to the manufacturer's diagram.

Supply Supply conductors Usually Where you find it
230 V single-phase 1 phase + neutral 2P Most homes, like the example house.
230 V single-phase on a 3 × 230 V network 2 phases, no neutral 2P Older networks, in part of the country.
3 × 230 V 3 phases, no neutral 3P Three-phase on those same older networks.
3 × 400 V + N 3 phases + neutral 4P New builds and homes with heavy loads such as a heat pump or a charging point.
Careful with blue: a 3 × 230 V network has no neutral. There, the blue conductor can also be a phase and be live.

Why the earthing belongs on the plan

All metal enclosures and the green-yellow protective conductors are connected to the earth. If a live conductor touches a metal cabinet somewhere, the current flows away to earth instead of through whoever touches the cabinet. That is why the inspector measures the earth resistance of the earth electrode. The AREI aims for at most 30 Ω and never allows 100 Ω or more in a home. Between 30 and 100 Ω, stricter rules apply to the RCDs (lesson 5).

the supply is already there

  1. A new project starts with a meter, a 300 mA main switch, a distribution board and earthing. You don't have to draw them yourself.
  2. Click the main switch and set Number of poles to the number of poles of the device: usually 2 for a single-phase supply and 4 for 3 × 400 V + N.
  3. If you work with an account, also set the current type in the Project details tab. It appears at the bottom of every printed page.
1wire with the symbol library Add components on the left and on the right a drawing sheet with only the supply: earthing, meter, 300 mA main switch and an empty distribution board.
The starting point: the supply and an empty distribution board, with the library on the left.
Manual: setting the current type → Manual: changing a symbol →

Choosing circuit breakers

After this lesson you choose the right circuit breaker for each circuit and draw the first circuits on the board.

Each circuit starts on the board with its own protective device. It protects the cable against too much current, because a conductor that has to carry too much current heats up and can start a fire. Too much current arises in two ways:

  • Overload: too many appliances run on the same circuit at once. Think of an iron, a kettle and a fan heater on the same extension lead.
  • Short circuit: the phase touches the neutral or another phase directly, for example when someone drives a nail through a cable in the wall.

A circuit breaker or a fuse protects against this: both then switch the circuit off.

Circuit breaker or fuse?

In everyday speech they are used as synonyms. Many people say “the fuse has blown”, even when the board has a circuit breaker. Technically they are two different devices:

  • A fuse contains a thin wire that melts when the current is too high, after which you have to replace it. You still find them in older homes.
  • A circuit breaker switches off by itself, and once the cause is fixed you simply switch it back on. New installations almost always have circuit breakers.

Both protect the cable against overload and short circuit, but they are not interchangeable at the same rating: on 2.5 mm² a circuit breaker may go up to 20 A, a fuse only up to 16 A (see the table below). If an older home has fuses, you draw fuses, because the plan shows what is actually there.

The label

Next to each circuit breaker you write its characteristics. For (sockets) of the example house that is 2P - C 20A with a box 3000:

2Ptwo poles: both conductors (phase and neutral) are switched
Cthe tripping curve; C is the usual choice in homes
20Athe rated current: how much may flow through the circuit continuously; above that the breaker trips, faster the higher the current
3000the breaking capacity in amperes: the largest short-circuit current it can safely interrupt

Where to find this on the breaker itself

The same data is on the front of every circuit breaker in the board, usually just below the brand. So you can fill in the diagram simply by looking in the distribution board:

  • C20 (or “C 20”): curve C and the rated current of 20 A.
  • 3000 in a box: the breaking capacity in amperes. Copy it into the box on the diagram.
  • The number of poles is usually not written on it. The number of terminal screws at the top is a first clue: two on a two-pole, four on a four-pole breaker. Also look at the marking and the small wiring diagram on the device. That way you can tell a 2P from a 1P+N: the latter also has two terminals, but only protects the phase. An N next to a terminal shows where the neutral goes.
  • The manufacturer's type code (such as VYC32), the voltage (400V~) and the small digit under the box (the energy limiting class) don't need to go on the diagram.
A two-pole circuit breaker with two terminal screws at the top. Circled below the brand: the type code, C20, 415V~, the breaking capacity 3000 in a box and a 3 below it.
Two-pole (2P): two screws, C20 and 3000.
A four-pole circuit breaker with four terminal screws at the top and an N at the last pole. Circled below the brand: the type code, C 20, 400V~, the breaking capacity 3000 in a box and a 3 below it.
Four-pole (4P): four screws, the last pole marked N.

Thicker cable, bigger breaker

Which breaker you choose depends on the cross-section of the cable behind it. A thin conductor can carry less current, so it needs a smaller protective device. The table gives the upper limit per cross-section in a home (AREI, table 4.11); a bigger breaker is never allowed. Whether a combination is really suitable also depends on the load, the installation method and the length of the cable (voltage drop). The electrician works that out. For the same cross-section, the limit for a fuse is lower than for a circuit breaker.

Cross-section Max. circuit breaker Max. fuse In the example house
1.5 mm² 16 A 10 A Lighting and : 16 A
2.5 mm² 20 A 16 A Sockets, oven and appliances: 20 A
4 mm² 25 A 20 A —
6 mm² 40 A 32 A Single-phase hob : 32 A
10 mm² 63 A 50 A Supply to a board or a large load

the first circuits on the board

  1. In the group Cables, circuit breakers and RCDs, click Circuit breaker with cable. Insert mode switches on.
  2. Blue insertion points appear on the drawing sheet. Click the distribution board to add the circuit. Draw the hob and the oven this way, the two circuits that go directly on the main board. Press Escape to stop. The circuits behind the 30 mA follow in lesson 5.
  3. Click a circuit breaker and fill in Number of poles, Current, Curve and Short-circuit current in the panel on the left. The label next to the symbol updates immediately.
  4. Is there a fuse in the board? Then choose Fuse instead of Circuit breaker under Type.
The drawing sheet in insert mode: blue insertion points on the circuits and on the rails, with the message at the bottom asking you to click an insertion point to insert the symbol there.
In insert mode, blue circles show where the symbol can go.
The Circuit breaker panel of circuit F: type Circuit breaker, 2 poles, short-circuit current 3000, current 20 A, curve C.
The panel of the breaker of circuit F. Each field becomes part of the label; the breaking capacity is called Short-circuit current here.
Manual: adding a symbol →

The 30 mA RCDs

After this lesson you know which circuits go behind a 30 mA RCD, what changed about that in 2023, and you draw each RCD with its own rail.

An RCD (residual current device, also called a differential switch) compares the current that leaves through the phase with the current that comes back through the neutral. If current leaks away somewhere, for example to earth through a faulty washing machine or through someone touching a conductor, less comes back. That difference is the leakage current. If it gets too large, the RCD trips within a fraction of a second.

  • The 300 mA main switch from lesson 3 protects the whole house, mainly against fire caused by leakage currents.
  • An additional 30 mA RCD is much more sensitive and protects people against electric shock.

Which circuits behind 30 mA? The rules since 1 June 2023

On 1 June 2023 the AREI rules for homes became stricter. For a new installation the rules are now, if the earth resistance is at most 30 Ω:

  • Behind a 30 mA RCD: the bathroom, the washing machine, the dryer and the dishwasher, and now also the lighting and the sockets that are not intended for a fixed appliance.
  • At most eight circuits behind each 30 mA RCD.
  • Fixed appliances such as the hob, the oven, a fridge or electric heating may go directly behind the 300 mA.
  • If the earth resistance is between 30 and 100 Ω, there must be at least two 30 mA RCDs, each with at most sixteen sockets; a fixed appliance counts as a socket. The other circuits then go behind an RCD of at most 100 mA. We don't go further into that special case here.

The diagram shows the type and characteristics of each RCD. In a home, type A is the minimum, and the RCD at the origin of the installation is rated at least 40 A.

The example house follows these rules. protects the lighting and the sockets (, and ), the washing machine, the dryer, the dishwasher and the bathroom (H to K). A single RCD for all seven circuits would also be allowed, but with two, a leakage current only cuts off part of the house. In a larger house, the lighting is often spread over both RCDs, so that the lamps never all go out at once.

On the diagram, each RCD sits on the main board, with its own rail behind it. All circuits on that rail are protected by the 30 mA. Each circuit still keeps its own circuit breaker: the RCD watches for leakage current, the breaker for overload and short circuit.

RCD C with Type A, 30 mA, 2P - 40A and behind it a rail with circuits D and E (lighting) and F (sockets); RCD G with the same values and behind it a rail with circuits H washing machine, I dryer, J dishwasher and K bathroom.
The two 30 mA RCDs, each with its own rail: C for lighting and sockets, G for laundry and bathroom.

The label

For both RCDs of the example house you write Type A - Δ30mA, 3000 and 2P - 40A. Don't mix up two numbers:

  • 40A is the current the device may carry continuously. An RCD does not protect itself against overload; so don't choose it smaller than the protection of the supply, 40 A in the example house.
  • Δ30mA is the leakage current at which it trips. On the device it is often given in amperes: IΔn 0,03 A is 30 mA, IΔn 0,3 A is 300 mA. On the diagram you write milliamperes.
  • Type A also detects leakage currents from electronic appliances. It is compulsory in homes; the older type AC has no longer been allowed since 2023, not even in existing installations.

What it says on the RCD itself

Look in the distribution board and you will find everything you need for the diagram on the front of the RCD:

  • 40 A: the current the device may carry.
  • IΔn 0,03 A or IΔn 0,3 A: the leakage current, in amperes. Convert to milliamperes: 0.03 A = 30 mA and 0.3 A = 300 mA.
  • A with a small wave in a box: the type, here type A.
  • T: the test button. Press it as often as the manufacturer says; the RCD must then trip.
  • The number of poles: count the terminals at the top, just as on a circuit breaker. Two terminals (phase and N) is 2P, four is 4P.
A 30 mA RCD. Circled: the marking 40 A / IΔn 0,03 A with the blue test button T, and below it the wiring diagram with the type A symbol.
30 mA: “40 A / IΔn 0,03 A”, type A.
A 300 mA RCD. Circled: the marking 40 A / IΔn 0,3 A, the blue test button T and the type A symbol.
300 mA: “40 A / IΔn 0,3 A”, type A.

What an older installation often looks like

Many homes were wired before June 2023. There, the lighting and the sockets often sit directly behind the 300 mA, and there is only one 30 mA RCD, for the bathroom and the laundry. The 2023 rules apply first and foremost to new installations. For existing installations and for minor changes or extensions to existing circuits, the AREI provides exemptions and transitional rules. Some new rules do apply to everyone, such as the ban on type AC. Whether your installation is in order is for the inspector to judge.

Parts installed before 1 October 1981 are marked “old installation” (“oude installatie”) on the single-line diagram.

If you draw an existing house, draw what is actually there, even if it looks like the example below. Never adjust the plan to the rules: the inspector compares the plan with the installation.

A single-line diagram as often seen in older homes: circuits A to E (lighting, sockets, hob and oven) directly on the main board behind the 300 mA, and a single 30 mA RCD F with circuits G to J for washing machine, dryer, dishwasher and bathroom.
A layout you often see in older homes: lighting and sockets (A to C) directly behind the 300 mA, and a single 30 mA RCD (F) for the laundry and the bathroom.

the RCDs and their rails

  1. In Cables, circuit breakers and RCDs, choose the Type A 2-pole differential switch and click the main board.
  2. Add a Distribution board behind it: that is the rail for the circuits behind the 30 mA. With Circuit breaker with distribution board you place both in one go.
  3. On that rail, draw the circuits for the lighting and the sockets, each with a Circuit breaker with cable.
  4. Repeat for the second RCD, with the circuits for the washing machine, dryer, dishwasher and bathroom.
  5. Check Residual current (30 mA), RCD type (A) and Current in the panel.

1wire also gives the branches with the RCDs themselves a letter, and , so you can refer to them by name. Their name stays empty.

The settings panel of the RCD: residual current 30 mA, RCD type A, 2 poles, current 40 A.
The settings of RCD C.

Cables and circuit names

After this lesson you write the right code next to every cable and give every circuit a name.

Above each circuit breaker, the cable runs to the points of the circuit. On the diagram that is one line with a code next to it. For of the example house it is VOB Eca 3G2,5:

VOBthe type: single insulated wires, pulled through a conduit
Ecathe fire class of the cable: how it behaves in a fire
3the number of conductors
Git includes a green-yellow protective conductor
2,5the cross-section of each conductor in mm² (with a decimal comma)

Besides VOB you will often come across XVB: a cable with a sturdy outer sheath that may also be laid on or in a wall without conduit. Underground it goes in a conduit; where and how a cable may be laid is in the manufacturer's data sheet. Choose the cross-section to match the breaker from lesson 4: 1.5 mm² for lighting, 2.5 mm² for sockets and most appliances. The small marks on the line show how the cable is installed. In 1wire the two E marks mean “built into the wall” and the small circle “in conduit”.

Junction and connection boxes also belong on the diagram. In 1wire you find them in the Branch points group.

Labels: letter plus number

Within a circuit, each point gets a sequence number. That creates a label such as : circuit F, point 3. That label later also appears on the floor plan, and that is how the two plans are linked. Also give each circuit a clear name, such as “Lighting first floor”. That helps the inspector, and later the occupant when something fails.

The colours of the conductors

You don't draw colours on the diagram, but you need to know them to compare the diagram with the installation:

Conductor Colour Function
Protective conductor (PE) green-yellow connects metal parts to earth; never use it for anything else
Neutral (N) blue the return path of the current
Phase (L) brown, black or grey the conductor that is live
Don't rely on colour alone. Older installations still have other colours, and on a 3 × 230 V network a blue conductor can also be a phase (lesson 3).

filling in the cable and naming the circuit

  1. Click the line above a circuit breaker. In the Wire panel, choose Cable type, Fire class, Number of conductors, Placement and Cross-section, and tick Protective conductor. 1wire writes the code next to the line itself.
  2. At the bottom of the panel, under Circuit, fill in the Circuit name.
  3. 1wire assigns the letters and sequence numbers automatically. With Circuit names and Sub-circuit names at the top of the drawing sheet you show or hide the names.
The Wire settings panel of circuit F: cable type VOB, fire class Eca, 3 conductors, placement in wall, cross-section 2,5 mm², in conduit and protective conductor ticked.
Together these fields make “VOB Eca 3G2,5”.
Manual: automatic numbering → Manual: circuits and sub-circuits →

Lighting and switches

After this lesson you choose the right switch for one, two or three switching points and draw the lighting circuits.

A light point is a small cross. A switch is a small circle with a slanted arm. The shape of that arm tells you which kind of switch it is. Which one you choose depends on from how many places the light must be switched:

Switch Symbol When do you choose it?
Single-pole Single-pole switch symbol: one slanted arm One lamp or group of lamps, switched from one place. The switch only breaks the phase.
Double-pole Double-pole switch symbol: one arm with an extra cross stroke Breaks both phase and neutral. A good choice in damp rooms such as the bathroom.
Two-way switch Two-way switch symbol: arms on both sides of the circle Always in pairs: switching one lamp from two places, such as the top and bottom of a staircase.
Intermediate switch Intermediate switch symbol: four arms, like a cross Between two two-way switches, for three or more places. Each extra place is one more intermediate switch.
Rule of thumb: in a classic circuit with two or more switching points, the first and the last switch are two-way switches. Everything in between is an intermediate switch. Four places therefore gives two-way – intermediate – intermediate – two-way.
Many switching points? Then people often choose push buttons with an impulse relay in the board: each press of a button turns the light on or off, however many buttons there are. In 1wire you find them in the Switches, push buttons and relays group.

The lighting of the example house

  • , living room: two lamps that are always on together, with one single-pole switch. You draw one cross with “x2”.
  • , stairs: a two-way switch downstairs and one upstairs, with one lamp.
  • , bedroom: switches at the door and on both sides of the bed, so two-way – intermediate – two-way.
  • , landing: a single-pole switch.

Each lamp with its switches is one point on the circuit. Two lamps you want to switch separately become two points.

Circuits D and E. Circuit D: point 1 a single-pole switch with two lamps, point 2 two two-way switches with a lamp. Circuit E: point 1 two-way, intermediate and two-way switch with a lamp, point 2 a single-pole switch with a lamp.
This is what it looks like once circuits D and E are drawn.

switch and lamp in one go

  1. Open the Light points, spotlights and LEDs group with the arrow next to the number of variants.
  2. Choose the combination that fits the point: Switch + light, 2-pole switch + light, 2x Switch + light (two two-way switches) or 3x Switch + light (two-way, intermediate, two-way).
  3. Click an insertion point on the cable. For two lamps on one switch, set the quantity of the light point to 2.
  4. Need to change a switch later? Click it and tick Two-way switch or Intermediate switch, or set Number of poles to 2.
The Light points, spotlights and LEDs window with variants such as Light point, Switch + light, 2-pole switch + light, 2x Switch + light and 3x Switch + light.
The variants of Light points, spotlights and LEDs.
The Switch settings panel of the middle switch of E1: 1 pole, Intermediate switch ticked.
The middle switch of E1 is an intermediate switch.
Look up all symbols →

Sockets and appliances

After this lesson you draw sockets and fixed appliances, and choose the cable for a hob.

A socket is a half arc with a short stroke: the stroke is the earth. A double socket gets two arcs side by side, a triple three. On you draw five socket groups: single at points 1, 2 and 4, double at points 3 and 5.

Sockets in a home must have child protection: shutters that close off the holes. On the diagram you see this from the short strokes at both ends of the arc.

Fixed appliances are small squares with their own sign inside. is the hob (four cooking zones), the oven. Each appliance gets its own circuit breaker and cable.

A small “h” next to a symbol means it is waterproof. You use it in the bathroom: for the lamp, the switch and the socket of . That letter alone does not make equipment suitable for every spot: in a bathroom, the zones around the bath and shower determine which equipment is allowed where and what degree of protection (IP) it needs.

is a mixed circuit: lighting and a socket together. Because there is a socket on it, the rules for a socket circuit apply to the whole circuit: at least 2.5 mm² and at most eight points. A light point, or a group of lamps with one common switch, counts as one socket.

Circuit F with five socket groups numbered 1 to 5, of which 3 and 5 are double, with VOB Eca 3G2,5 and 2P - C 20A.
Circuit F: sockets.
Circuit A, the hob with VOB Eca 3G6 and 2P - C 32A, and circuit B, the oven with VOB Eca 3G2,5 and 2P - C 20A.
Circuit A (hob) and B (oven).

The hob: the appliance determines the connection

A hob needs a lot of power. In the example house, with a single-phase supply, we choose a 3G6 cable with a 32 A circuit breaker. On a three-phase supply, a hob can spread its power over two or three phases; that needs more conductors, but a smaller cross-section is often enough. How a hob is connected is in the wiring diagram of the appliance itself; the electrician chooses the cable and breaker accordingly. On the diagram you copy what is actually there.

Charging point, solar panels and heat pump

New heavy loads also each get their own circuit with their own circuit breaker. A charging point needs an RCD that also detects DC leakage: a type B, or a type A together with 6 mA DC detection, which many charging points already have built in. Follow the charging point's manual for this. Solar panels connect through the inverter to their own circuit. In 1wire, the charging point and the heat pump are under Devices, the inverters under Solar panels and batteries. For a home battery with backup power there is a separate guide: drawing a backup power circuit.

adding sockets and appliances

  1. In the Sockets group, choose a Socket, 2 sockets or 3 sockets and click the cable of the circuit. Every socket you add gets its own sequence number.
  2. Child protection is on by default in the panel; leave it on in a home. Tick Waterproof where needed.
  3. The oven, washing machine, dryer and dishwasher are in the Devices group; the hob is called Cooker there.

Everything you draw automatically ends up in the Material list. Handy for checking that you haven't forgotten anything.

See a material list → Manual: the material list →

Drawing up the floor plan

After this lesson you draw the plan of each floor and put every point from the diagram in the right place.

The floor plan is a plan of each floor with the symbols from the diagram. Below each symbol is its label. That label is the bridge between the two plans: on the diagram is exactly the same socket as F3 on the floor plan.

You draw up the floor plan in three steps:

  • The plan. Draw the walls, doors and stairs of each floor. It doesn't have to be an architect's drawing: the rooms must be recognisable and the proportions right.
  • The points. Put every light point, switch, socket and appliance where it actually is.
  • The distribution board. Also show where the board is.
Floor plan of the ground floor: living room with lamps D1 and sockets F1 to F5, kitchen with dishwasher J1, hob A1 and oven B1, hall with stairs and lamp D2, utility room with washing machine H1 and dryer I1.
The ground floor of the example house: each symbol carries the label from the single-line diagram.

One label, several places

Sometimes more than one symbol carries the same label. Everything with the same label belongs to the same point. Take , the stair lighting: you put the lamp and one two-way switch downstairs in the hall, the second two-way switch upstairs on the landing. So the first floor also has a D2, even though it is on the ground-floor lighting circuit. In the bedroom you place three times: at the door and on both sides of the bed.

Floor plan of the first floor: bedroom with lamp E1 and three switches E1, bathroom with lamp and switch K1 and socket K2, landing with stairs, switch D2 and lamp and switch E2.
The first floor: three switches E1 in the bedroom and the second switch of D2 at the top of the stairs.

drawing the plan and placing the points

  1. Open the Floor plan tab. Rename the first floor and add another with New floor.
  2. Draw the walls with Straight wall, and add doors, windows and the stairs with Door, Window and Interior. Use Board to mark the distribution board and Text for the room names. If you already have a plan as an image or PDF, you can import it with Image.
  3. On the left, under Place components, are all points from your diagram, per circuit. Click a symbol and then the plan to place it. The R key rotates it.
  4. Filter on Unplaced to see what is still missing.

Feel free to work with both plans side by side: in the single-line diagram, click Floor plan at the top right. Select a symbol on one side and it lights up on the other side too.

1wire in split view: on the left the single-line diagram with the switch of D1 selected, on the right the floor plan of the living room where the same switch lights up.
Split view: on the left the switch of D1 is selected. On the right it lights up too, with dotted lines to the two lamps it switches.
Manual: drawing the floor plan → Manual: placing symbols → Manual: importing a plan →

Checking and printing

After this lesson you check your plan with a checklist and print it as a PDF.

Before you hand the plan to the inspector, go through it once from start to finish. This checklist follows the same order as the lessons:

The supply

Meter, main switch with type, poles, current and Δ300mA, distribution board, earth disconnect link and earthing. The voltage and type of current, for example 230 V AC.

Every circuit

A letter, a clear name and a circuit breaker with poles, curve and current that match the cable.

The RCDs

For each RCD the type, the leakage current and the current. New installation: lighting, sockets, bathroom and laundry behind 30 mA, at most eight circuits per RCD.

Every cable

Type, fire class, number of conductors and cross-section, for example VOB Eca 3G2,5. No line without a code.

Every point

The right symbol for every switch, lamp, socket and appliance. At most eight sockets per circuit, with child protection. The junction and connection boxes too.

The floor plan

Every floor, the distribution board and every point with its label. Nothing left under “Unplaced”.

The plan matches the house

A plan that is neatly drawn but doesn't match what is in the walls helps nobody. So compare the diagram with the distribution board itself: every breaker on the board belongs on the diagram, with the same value. That also applies to an older installation that doesn't meet the 2023 rules: the plan shows the installation as it is. If something changes in the installation later, update the plan too.

checking and making the PDF

  1. Check the circuits in the Circuits tab and the material in the Material list.
  2. The Not placed on floor plan button in the single-line diagram shows how many points are not yet on the plan.
  3. In the Project details tab, fill in the installation address, the EAN code, the electrician and the inspection body. They appear at the bottom of every page. That tab appears as soon as you work with an account.
  4. Open the print screen with the printer icon at the top. Choose A4 or A3, tick the parts and click Export PDF. If the diagram doesn't fit on one sheet, 1wire spreads it over several pages; a dotted line on the drawing sheet shows where a page ends.
The Print / Export screen with paper size A4 or A3, options to scale down the single-line diagram or print it in portrait, and tick boxes for the single-line diagram, floor plan, circuit list, domotics and material list, with the Export PDF button at the bottom.
The print screen: choose what goes into the PDF.

Drawing in 1wire is free. You only pay when you want to print the plan without restrictions.

Manual: printing and exporting → Manual: filling in the project details →

Bonus: your plan when something fails

A good plan really proves its worth when something goes wrong. If breaker trips in the example house, the diagram tells you that E is the lighting of the first floor, with points (bedroom) and (landing). On the floor plan you see straight away where they are. If trips, the washing machine, the dryer, the dishwasher and the bathroom all go off at once. That often points to a leakage current in one of those appliances. Unplug them, switch G back on and plug them in again one by one: if G trips again, you know which appliance an electrician should take a look at.

Please note: these lessons teach you to draw up a single-line diagram and floor plan that correctly represent an installation. The choices in the example house follow common rules for homes. For a real installation the AREI remains the standard, and the inspector checks whether the plan and the installation match. Leave work on the installation itself to an electrician.

Sources (in Dutch): the AREI, Book 1 (low-voltage installations), 2026 edition, published by the FPS Economy, and Volta's overview of the changes of 1 June 2023. Last checked: October 2026.

Draw up your first single-line diagram

Start with the supply, add the circuits one by one and then put everything on the floor plan. Free, in your browser, nothing to install.

Open an empty drawing sheet

Questions about drawing up a single-line diagram

What is the difference between a single-line diagram and a floor plan?

The single-line diagram shows how everything is connected electrically: protective devices, cables, switches and loads. The floor plan shows where those parts are in the house. Together they form the plan of the installation; labels such as F3 link them to each other.

Why is it called a “single-line” diagram?

Because one line represents the whole cable, even though it contains several conductors. The number of conductors and their cross-section are given in a code next to the line, for example 3G2,5.

When do you need a single-line diagram?

At every inspection: before a new installation is put into use, when a house is sold and after a major extension or modification. The inspector lays the single-line diagram and the floor plan next to the installation. Afterwards they belong in the electrical file of the house.

I'm drawing an existing house. Does my diagram have to look like the one in the lessons?

No. The example house follows the rules for a new installation from after June 2023. An existing installation often looks different, for example with the lighting and sockets directly behind the 300 mA. You always draw what is actually there. Lesson 5 shows what such an older installation looks like.

Do I have to date and sign the plan?

Not as the owner: since 1 June 2023 the owner no longer has to date and sign the single-line diagrams and floor plans. If the installation passes the inspection, the person responsible for carrying out the work and the approved inspection body do sign and date them. Each plan also carries a number, a version and the date of that version. For a new installation or a major modification, the name and capacity (and VAT number) of whoever did the work also appear on the plans, as does the address of the installation.

How long does it take to draw up a single-line diagram?

The drawing itself is quick: for an ordinary house with about ten circuits, once you know the lessons, allow a few hours for the diagram and the floor plan. 1wire numbers the circuits and points itself and keeps both plans linked. In an existing house, tracing the circuits often takes longer than the drawing, especially if nothing is labelled on the board.

I'm studying electrical engineering. Can I use 1wire for free to practise?

Yes. You can start drawing in the browser right away, without an account. For students and teachers there is also a free student account. Diagrams from a student account cannot be used as an official AREI plan, though.

I only have an old plan on paper. Do I have to start from scratch?

No. With 1wire you can scan a photo or PDF of an existing single-line diagram. It is converted into an editable diagram that you can check and complete with these lessons.

Where can I find a symbol that isn't in these lessons?

The single-line diagram symbols page lists every symbol you can draw in 1wire, with its meaning. For a home battery or an inverter with a backup output there is a separate guide: drawing a backup power circuit.

After these lessons, may I work on my installation myself?

These lessons teach you to draw up the plan, not to build or change the installation. Work on the installation must comply with the AREI and is checked at the inspection. Leave that work to an electrician.